<p>Woodstock- Hartland NH FPAV (50)</p>

<p>US Route 4 Paving Project</p>

<p>DATE: Friday, October 21, 2022</p>

<p>TRAFFIC IMPACT AND DURATION: Monday, October 24 through Friday, October 28, between 7 a.m. and 6 p.m., motorists can expect a single-lane closure with alternating one-way traffic. Flaggers will be in place to assist motorists.</p>

<p>CONSTRUCTION ACTIVITIES: Crews will be line striping the roadway, paving gutters, and conducting shoulder work throughout the week. All work is weather dependent.</p>

<p>LOCATION: Woodstock-Hartland NH FPAV(50): Beginning on U.S. 4 near Sawyer Road and continuing for approximately 3.1 miles, ending at the intersection of U.S. 4 and VT 12 in Hartland.</p>

<p>PROJECT COMPLETION: Fall 2022</p>