Construction Update

Posted Friday, September 23, 2022
Notices

<p>Construction Update<br /> Woodstock- Hartland NH FPAV (50)<br /> US Route 4 Paving Project<br /> DATE: Friday, September 23, 2022</p>

<p>TRAFFIC IMPACT AND DURATION: Monday, September 26 through Friday, September 30, between the hours of 6 a.m. and 6 p.m., there will be a single-lane closure with alternating one-way traffic on US Route 4 (US 4). Flaggers will be in place to assist motorists. Traffic delays are expected.</p>

<p>CONSTRUCTION ACTIVITIES: On Monday crews will be backing up timber treated curbing with recycled asphalt. Tuesday and Wednesday, crews will be preparing the roadway for paving, including filling potholes.<br /> Paving is tentatively scheduled to begin on Monday, October 3. Paving is weather dependent.</p>

<p>LOCATION:<br /> Woodstock-Hartland NH FPAV(50): Beginning on US Route 4 near Sawyer Road and continuing for approximately 3.1 miles, ending at the intersection of US Route 4 and Vermont Route 12 in Hartland.</p>

<p>PROJECT COMPLETION: Fall 2022</p>

<p>Contact Information:<br /> Name - Delia Makhetha<br /> Phone - 603-263-8881<br /> Email - delia.makhetha@wsp.com</p>